Schluter-KERDI-SHOWER-LT
How to install
To install KERDI-LINE-H with a horizontal drain and odour trap, start by precisely fitting the channel support and channel body. The components can be adhered with thin-bed tile adhesive, provided the substrate is level and height-adjusted.
Properly install the levelling layer (compressive strength >= 0.3 N/mm²) on the weight-bearing substrate. Make sure that the upper edge of the levelling layer is situated approx. 24 mm below the linear drainage. If using bound fillings, it may be advisable to apply spackle prior to installing the tray, depending on the condition of the substrate. The respective manufacturer’s specifications must be observed.
Note:
If impact sound insulation is required, install suitable impact sound insulation underneath the levelling layer and KERDI-LINE-H (e.g. KERDI-LINE-SR) together with the corresponding edge strips.
To install the vertical linear drainage KERDI-LINE-V, adhere the sloped tray directly on a suitable substrate at the appropriate height.
Notch the sloped tray at the pre-marked cutting grooves with a utility knife, depending on the selected dimension of KERDI-LINE.
Then embed the sloped tray fully in thin-bed tile adhesive to be flush with the KERDI-LINE channel support. Slide the small groove of the adjoining sloped tray surface laterally below the flange.
Now attach the KERDI collar that is pre-adhered at the linear drainage to the adjoining waterproofing of the sloped tray, using the sealing adhesive Schlüter-KERDI-COLL
Colour | N/A |
---|---|
Product Code | KSL-Shower-Tray |
Manufacturer | Schluter |